Details
Beam Bridge
Executive plan
Location
Monreale (PA) – S.S. No.118 “Corleonese – Agrigentina”
Principal
TECNIS S.p.A
Contracting company
- TECNIS S.p.A.
- COGIP S.r.l.
- SIGENCO S.p.A.
Team
- Matildi+Partners S.r.l.
- TECNIS S.p.A.
- SAB Engineering S.r.l.
Activities
Executive plan (scaffolding)
Time Period
2007-2010
Extent and spans
140 m | 30+40+40+30
![](https://www.matildi.com/wp-content/uploads/2023/09/0_Anteprima-Scalilli-1.jpg)
Structural Layout
![Structural Layout](https://www.matildi.com/wp-content/uploads/2023/09/1_Schema-strutturale-Scalilli-e1700128519825.jpg)
Structural Layout
Detailed executive plan of the metal deck of the Scalilli viaduct as part of the works for the arrangement and adaptation of the road platform between 18 + 700 km and 24 + 650 km of S.S. No. 118 “Corleonese – Agrigentina”.
The new deck is a continuous truss in a composite steel-concrete system with a caisson layout equivalent to four spans of 30+40+40+30 m. The structure in plan view is symmetrical with respect to the radial barycentric axis and exhibits the initial and final section in a Euler spiral, while the central section is of constant curvature with a radius of curvature of 338 m.
The concrete slab accommodates a road platform and two pavements, with a total width of 17.25 m, including a widening area for visibility.
It is frame worked on 3 double-T flanked beams; their spacing is 5.50 m at the extrados and 3.70 at the intrados.
The slab, with a total thickness of 30 cm, is cast in situ on self-supporting concrete predalles.
Deck and Assembly
![Deck and Assembly](https://www.matildi.com/wp-content/uploads/2023/09/2_Impalcato-e-montaggio-Scalilli.jpg)
Deck and Assembly
Both internal and external beams have a constant height of 2.00 m, while the external beams are inclined at an angle of approximately 48° to the normal axis of the lower jack arch.
They are connected by lattice-type diaphragms positioned at a constant centre distance of 5 m and by a lower bracing in the form of a St. Andrew’s cross, which is required to ensure torsion-rigid caisson behaviour.
Assembly of the deck is carried out by lifting the individual beams from below with the aid of a crane truck, after assembly of the segments on the ground and subsequent forward advancement.