Details
Detailed executive plan for 5 viaducts in a composite steel-concrete system, of which 4 on the main axis on a dual carriageway and 1 on the ring road on a single carriageway. Current composite system sections consist of pairs of double-T beams with a height of 2 m, working together with concrete slabs between 12 m and 16.75 m wide
Structural tipology:
Beam Bridge
Beam Bridge
Location
SS 199 “Monti” – from 61+600 km to 68+600 km
Olbia – SS
Principal
ANAS S.p.A
Contracting company
Oberosler cav. Pietro S.p.a.
Team
Matildi+Partners srl
Activities
Executive plan (scaffolding)
Time Period
2014 – 2016
Designed Works
5 Viaducts
– VI01 – Su Gugguttu Viaduct
– VI02 – Cannalzos Bridge
– VI03 – Rio San Michele Viaduct
– VI04 – Rio San Michele Viaduct Secondary road
– VI05 – Sa Piana Viaduct