Open detail Hide detail

Details

Detailed design of the composite steel-concrete deck of the bridge over the River Rienza as part of the works for the completion of a new access road in Val Badia, lot Bosco del Convento, on S.S. 244 “Val badia”
Structural tipology:
Gantry Bridge
Design level:
Executive plan
, Final design plan


Location

New access to Val Badia with bridge over the Rienza and Floronzo tunnel – Bosco del convento lot – S.S. 244 “Val badia” – San Lorenzo di Sebato (BZ)

Principal

Cimolai S.p.A

Contracting company

  • Strabag S.p.A.
  • Alpenbau Srl
  • Unionbau S.p.A.
  • Moser&Co Srl
  • GeObau Srl

Team

  • MC Engineering
  • Matildi+Partners srl

Activities

Executive plan (scaffolding)

Time Period

2019-2021

Extent and spans

147 m | 59+85

Bridge over the Rienza

Structural Layout

Structural Layout

Structural Layout

Detailed design of the composite steel-concrete deck of the bridge over the River Rienza as part of the works for the completion of a new access road in Val Badia, lot Bosco del Convento, on S.S. 244 “Val badia”.

The new deck is a continuous truss in a composite steel-concrete system with a gantry design, divided into two spans of 58.67 m and 85.33 m.

The Deck

The Deck

The Deck

The concrete slab accommodates the road platform and two pavements with an overall width of 12.00 m; it is framed on the main beams, which are 7 m apart, and on the intermediate pin beam. The slab is cast in place on self-supporting metal tiles 5 mm thick, until a total thickness of 25 cm is reached after additional casting.

The beams vary in height from a minimum of 1.6 m to a maximum of 2.8 m, and are connected by lattice-section diaphragms positioned with a constant pitch of 5.35 m, as well as by a lower bracing with a rhomboid pattern, which guarantees the torsion-rigid box functionality.

Assembly

Assembly

Assembly

Construction of the bridge was staggered, consisting of successive lifting of macro-segments assembled on the ground and connected at height by welding, only after the central trestle had been built. Assembly required the construction of three temporary piers and a temporary tie-rod.

Photo gallery

A visual narrative depicting our rigorous work on the design, construction and testing of the infrastructure as a new roadway serving the entire community.