Implementation of pier foundations on Piacenza side (summer 2001) -
Incremental launching of the box girder -
The two box girders with antennas prior to closure of the key segment -
Anchoring the stays to the deck -
Deck prior to slab casting -
Anchoring stay heads - State of progress
-
Anchoring stay heads - Replacement with new tropicalised heads -
Bolted joints - State of progress -
Bolted joints - replacement of bolts -
Abutments S1 – S2 – State of progress. Support with oversliding -
Abutments S1 – S2 – State of progress. Lifting by 40 cm and recentring -
Abutment S1 - Recentring device
Stayed bridge over the River Adda -S.S. no.591 "Cremasca" (LO)
BACKExecutive design of the Stayed bridge over the River Adda in Montodine - S.S. no.591 "Cremasca" (LO)
Stayed steel deck length 400 m, with spans 75+252+75 m - Central extrados box girder with square section and sides of approx. 5 m - Aerials with square section with sides of approx. 2.5 m taller than 50 m.
Years: 2009
References:
- Tecnis S.p.A.